Bhubaneswar, Jan 11: The 13.51 km doubling line between Kerejanga-Angul has been commissioned. Chief Commissioner of Railway Safety (CCRS) has authorised to run the trains at a maximum speed of 100kmph for the new double line. By this completion
, doubling be-tween Rairakhol to Angul is now completed for Sambalpur-Talcher doubling project. This is 85.3km out of 168.2 km of doubling. The doubling line was commis-sioned yesterda,
CCRS inspection was conducted December 28 last in this section. Pre-non interlocked work started January 5 and ended January 7 and Non-interlocked working started January 8. Based on the speed trials and inspections,
the broad gauge line has been sanctioned for passen-ger and goods upto a maximum speed of 100 kmph, ECoR sources here said.